The Demand Status is used in Resource Management to reflect the status of the origin source to which the resource has been demanded. The resources demand statuses can be viewed and analyzed in Resource Analysis.
The demand status reflects the status of the object to which it was planned, hence for example, a resource planned on a work task with demand status Committed reflects that the work task status is either Prepared, Released or Work Started.
There are four different statuses:
The following mappings are used to map the Origin Status from the different sources to the Demand Status field:
Source |
Origin |
Origin Status |
Demand Status |
Human Resources |
HR Absence |
Registered |
Committed |
|
|
Partly calculated |
Committed |
|
|
Calculated |
Committed |
|
|
Calculation Cancelled |
Committed |
|
Training events - Event Trainer |
|
|
Published | Planned | ||
Confirmed | Committed | ||
Completed | Completed | ||
|
Training events - Event Participant |
|
|
Waiting Approval |
|
||
Registered | Planned | ||
Confirmed | Committed | ||
Notified | Committed | ||
Absent | Completed | ||
Attended | Completed | ||
Projects |
Project Activity |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Project Resource Forecast |
|
|
|
|
|
|
Service and Asset | PM Action | Active | Planned |
Maintenance Order - Work Task | New | Planned | |
Under preparation | Planned | ||
Prepared |
|
||
Released |
|
||
Work Started |
|
||
Work done |
|
||
Reported |
|
||
Finished |
|
||
Compatible Unit | Confirmed | Planned |