Complete MRB Case

Explanation

This activity is used to complete a material review board (MRB) case. Once the user has taken action on all of the MRB disposition items on the MRB case and approved all checklist items (if any), the user can update the MRB case status to complete by clicking Complete.

Prerequisites

This activity requires all MRB disposition items to be completed and all existing checklists to be approved.

System Effects

As a result of this activity the status of the MRB case becomes Completed. The MRB quantity will be made available again.