Update Top Level Quantity

Explanation

This activity is used to update the order quantity on the top DOP order to be equal to the demand quantity on the DOP header. If the top DOP order has supply orders, an option is available as to whether or not to automatically adjust the quantity of the supply orders.

To update the quantity click Update Date/Quantity, then click update Update Top Level Quantity. If pegged supplies exist for the DOP top part, a message appears inquiring whether an automatic update for the supply should occur. If you choose not to update the quantity on the pegged order, a quantity alarm will be generated.

Prerequisites

This activity requires that a DOP structure is generated for a DOP header.

System Effects