Enter Purchase Order Authorization Rule

Explanation

Purchase Order Authorization Rule page is used to define the criteria for when the connected authorization routing template will be valid for a purchase order or purchase order change order.

When you try to release a purchase order or purchase order change order, or when you manually fetch an authorization template, the system checks for any purchase order authorization rules that fulfills the requirement. The system selects the authorization rule with the highest priority implied, i.e., 1 indicates the highest priority. For a specific site, you cannot have two purchase order authorization rules with the same priority number with Planned and Released status, but as soon as one has been closed a new one with the same priority can be created. A closed rule can be set again to Planned status with Changed to Planned in the header.

To ensure that the authorization routing template will be applied by the system, you can indicate that the purchase order must use a specific supplier, coordinator, etc. If you want the rule to be applicable to all purchase orders or purchase order change orders regardless of the value for a criterion, select the corresponding option.

The approval rule can have one of three status: Planned, Released, and Closed. The approval rule must be in the Released status to be used in the workflow.

You can also specify a minimum and a maximum amount in the authorization rule. The Use Gross AmountsĀ option is used to indicate whether the values specified as minimum and maximum are inclusive of tax. If the amount of the purchase order, or purchase order change order is within these values, the authorization rule will be used.

Enable the Valid for Original Authorization option if you want the rule to be used for authorization of the original purchase order revision. Enable the Valid for Change Order Authorization option if you want the rule to be used for authorization of purchase order change orders.

The Use Delta Amt. for Change Orders option is used to decide whether the full or changed amount since the last revision should be used in the authorization of the purchase order. This setting is only available if the authorization rule is valid for change order authorization.

The values in the Allow Changes After Authorization list are used to decide whether the total amount of the authorized or partially authorized purchase order can be modified or not. Possible values are No Changes Allowed, Within Order Amount and Within Authorizer Limit.

Apply for Non Project Connected PO indicates if this rule should be applicable for purchase orders or purchase order change orders which are not connected to a project.

Authorization Routing Option determines how the system includes steps (authorization lines) and validate steps in the authorization routing template to the authorization routing on the purchase requisition line or purchase order.

Prerequisites

System Effects