Perform Project MRP for Part
Explanation
Use this activity to run project MRP for parts, by using a project deliverable
structure.
Prerequisites
- An approved project deliverable structure with project defaults and
part information, must have been created.
- Parts should have been defined with the supply option Project MRP.
- Deliverable items must be approved.
- Project activity must be released.
System Effects
As a result of this activity, selective project MRP will be performed and
supplies will be planned for the inventory part(s).