Perform this activity to remove existing resource schedules, capacity and optionally; shift deviations.
This can for example be useful if generated schedule and capacity records no longer are valid for the resource or if schedules and capacity has been generated over a longer period of time for tactical planning and capacity analysis. Define a specific period for the records to be removed or define the From Date and leave the To Date blank to remove all records from the From Date and forward.
The Remove Resource Schedule and Capacity Information dialog can be accessed through the Aurena navigator.
Resource schedules and capacity records must have been generated.
Resource schedules, capacity and shift deviations will be removed for the defined time period.