Remove Shift Deviations
Explanation
Perform this activity to remove unwanted shift deviation records that
were created when the resource shift or break was added, edited or deleted.
Removal of shift deviations can be done for an individual record or for
multiple records using the Remove Deviation command. Moreover, all
deviations created against a scheduling resource can be removed through the
assistant when generating resource schedules and capacity.
Prerequisites
- A resource shift or break must have been edited, deleted or entered
manually to create shift deviations.
System Effects
- When a new shift has been added, it creates a shift deviation which
when removed, will also remove the created shift and the corresponding
record in calculated capacity.
- When the Shift Start and/or the Shift End has been updated, it
creates a shift deviation which when removed, will restore the latest
shift, and the corresponding record in calculated capacity.
- When the shift has been deleted, it creates a shift deviation which
when removed, will restore the shift and the corresponding record in
calculated capacity.