Create Risk Analysis
Explanation
This activity is used to create a new Risk Analysis.
The new record will automatically inherit some default values, some of which
have been explicitly defined as Basic Data in Risk Management.
Prerequisites
- A Risk Owner must be connected to the risk record and must be a registered
person in Person.
- The Risk Management default settings should have the default review
period defined.
- The currency must be defined and should be a valid value as defined
in Currency.
- A Site must exist. The sites that can be connected to a particular
Risk
Analysis depend on the Company associated with the particular Risk
Analysis record.
System Effects
- On saving the risk record, a Risk Analysis ID is created
with status Preliminary.
- The Person ID of the user creating the risk analysis will be
automatically entered as the Risk Owner, unless a Project
is selected, in which case the risk owner shall automatically be the
Project Manager.
- The Owning Company will automatically be set to the default company
for the user.