This activity is used to assign the scheduling priority of Work Tasks. It is achieved by adjusting the Per Hour Base Value defined on the Dynamic Work Scheduling Dataset. The default base value defined on the Dataset is assigned to all the Work Tasks planned using the dynamic Work Scheduling Dataset. That value can be overridden by defining hourly base value on Work Type/ Priority/ Object Criticality after enabling those tabs in the Dynamic Work Scheduling Dataset page.
Work tasks with higher calculated base value (Per Hour Base Value * Duration) has a higher probability of getting scheduled, over the Work Tasks that have a lower value.
ex:
Dynamic Work Scheduling Dataset Configuration:
per hour Base Value | |
Default | 20000 |
Work Type = 80 | 30000 |
Priority = 1 | 50000 |
Work Task Configuration:
Work Task No. | Duration | Work Type | Priority | Configured Task Value Result |
1100 | 1 | 20000 | ||
1200 | 1 | 80 | 30000 | |
1300 | 1 | 80 | 1 | 30000 + 50000 = 80000 |
For above example data, Task No 1300 has the highest probability of getting scheduled and Task No 1100 has the lowest probability.