Change Shop Order Earliest Start or Need Date

Explanation

Use this activity to change the earliest start or need date of the shop order.

When a shop order pegged to a DOP order or customer order line is rescheduled, the date change can be replicated based on the settings in Site/Manufacturing page. If the date change is not replicated to the DOP order, a time alarm is generated for the date mismatch between the DOP order and the shop order. If the DOP order has other supply orders, an error message appears, the due date of the DOP order is not changed and a time alarm is generated.

A time alarm may be resolved by either right-clicking and then clicking Update Dates From Supply or by updating the revised due date of the DOP order.

To change the earliest start or need date from the Shop Order, Shop Orders or Production Line Management/Shop Orders pages, enter a new value in the Earliest Start Date or Need Date field.

To change the earliest start or need date from the Inventory Parts Intraday Availability page, expand the line for the relevant part and select the supply line from the shop order you want to update. Click Edit Shop Order and enter a new value in the Earliest Start Date or Need Date field.

Prerequisites

System Effects