Edit Operation Result
Explanation
Use this activity to edit the result of on an existing operation report.
This includes reported scrap, quantity complete, labor and machine times. You
can adjust only the values reported on the original report transaction.
- To edit operation result from the Shop Floor Workbench
page, expand the operation and open the Reports
tab, then click Edit Result.
- To edit operation result from the Shop Floor Reports
page, click Edit Result.
- To edit operation result from the Time Card and
Time Card - Details pages. Select the relevant
report visible in the calendar area and click the Edit icon.
Prerequisites
To perform this activity:
- The status of the shop order may not be Closed.
- An operation report of the types Report Operation, Scrapping
in Operation or Report Labor must exist.
- Report may not be created from a shop floor clocking. If the report
is created from a clocking, result can only be adjusted by modifying the
start/stop time of the clocking record.
- If the Over Reporting list is set to Not Allowed on the
Inventory Part/Manufacturing tab, the sum of the reported
quantity complete and scrap must be equal to, or less than the planned operation
quantity plus the defined over report tolerance.
System Effects
As a result of this activity:
- A reversal operation or labor history transaction (UNOPFEEDĀ or
UNOPFDSCP) is created for the original operation report
transaction.
- A new operation or labor transaction history transaction (OPFEED,
OPFEED_SCP or LABOR_RPT) is created with the updated values.
- If the Adjust Schedule Due To Shop Floor Reporting option has been
enabled in the Shop Order Scheduling Basic Data/Shop
Order Scheduling/Scheduling Server tab, the schedule will be
adjusted to reflect the reported time.
- If Buffered Operations Reporting is enabled and the Adjust Schedule
Due To Shop Floor Reporting option is enabled in the
Shop Order Scheduling Basic Data/Shop Order Scheduling/Scheduling
Server tab, at the next execution of buffered
operations reporting the scheduling server will adjust the operation time
due to remaining quantity and:
- if Prioritize Reported Operation was chosen - the reported
operation is given priority and scheduled as close as possible to now
time.
- if Keep Scheduled Operation Sequence was chosen - the schedule
will be updated without altering the previous schedule sequence. Subsequent
operations in the same order structure will move closer to the reported
operation in order to fill any capacity gaps which occur immediately
after the reported operation.
- When having operation-linked material line with a connected supply pegging,
the issue will reduce the pegged quantity by the same quantity that was
issued. However, if there are more than one supply pegged to the same demand
you will be notified to manually adjust the pegging before the issue can
be performed.
- For project connected shop orders in IFS/Project, the Labor,
Set-up Labor, Machine and Set-up Machine Hours will
be reported to the project as actual hours according to the project cost
elements that have been defined in the Posting Control setup.