Report Machine Time
Explanation
Use this activity to report machine time for a shop order operation. It can
be the time needed to set up an operation before manufacturing begins (setup
time) or the time of the actual manufacturing (runtime). Machine time is
booked on a work center resource which does not have to be a machine, but
may also represent the physical location where the operation is performed.
Resource share indicates
how much the work center resource was utilized during its duration.
To report machine time for a shop order operation from:
- Shop Order Operations Reporting or
Work Center Operations Reporting page:
- Select an operation on the Internal Operations
tab and click Report or Report Scrap.
- Enter the time in the Machine Setup Time to Report
and/or Machine Time to Report fields.
- If
required, adjust the value in the Resource Share field.
- Shop Floor Workbench page:
- Select an
operation and click Approve or click Scrap
and enable Report Time.
- Enter the time in the Machine Setup to Report
and/or Machine to Report fields.
- If required, adjust the value in the Resource Share
field.
- Shop Floor Workbench page using the
Operation Guide assistant:
- Select an
operation and click Operation Guide.
- Click Approve or click Scrap
and enable Report Time.
- Enter the time in the Machine Setup to Report
and/or Machine to Report fields.
- If required, adjust the value in the Resource Share
field.
- Shop Floor Workbench/Reports tab:
- Select an operation, expand it and select the
Reports tab.
- Click New Result.
- Enter the time in the Machine Setup and/or
Machine Time fields.
- If required, adjust the value in the Resource Share
field.
- Shop Floor Reports page:
- Click New Result and then New Operation Result.
- Enter the time in the Machine Setup and/or
Machine Time fields.
- If required, adjust the value in the Resource Share
field.
Prerequisites
- The shop order operation must be in at least the Released status.
- To report machine time when reporting scrap, Report Time With
Scrap must have been enabled on the Work Center
page for the work center which to the operation belongs,
and you must also report some scrap quantity.
System Effects
- The status of the operation changes to either Setup Started,
Setup Complete or Partially Reported depending
on what you report.
- An operation history (OPFEED) transaction is
created.
- If the Adjust Schedule Due To Shop Floor Reporting option has
been enabled on the Shop Order Scheduling Basic Data/Scheduling
Server tab, the schedule will be adjusted to reflect the reported
time.
- If Buffered Operations Reporting is enabled and the
Adjust Schedule Due To Shop Floor Reporting option on the
Shop Order Scheduling Basic Data/Scheduling Server
tab has been selected, at the next execution of buffered operations reporting
the scheduling server will adjust the operation time due to remaining quantity
and:
- if Prioritize Reported Operation was chosen - the reported
operation is given priority and scheduled as close as possible to now
time.
- if Keep Scheduled Operation Sequence was chosen - the schedule
will be updated without altering the previous schedule sequence. Subsequent
operations in the same order structure will move closer to the reported
operation in order to fill any capacity gaps which occur immediately
after the reported operation.
- For project connected shop orders, the Machine Time and Setup
Machine
Time will be reported
to the project as actual hours according to the project cost elements that
have been defined in the posting control setup.