Add, Copy or Reset MS Level 0 Forecast Sets

Explanation

These activities are used to add two or more level 0 forecasts into one forecast or copy or reset forecasts.

When you copy a level 0 forecast from one master schedule set to another, you can copy from only one set at a time.

In addition, you can use this activity to restore the level 0 forecast of one or more master schedule sets. This activity is useful if you want to refresh the forecasts in a specific master schedule set, i.e., start over from the beginning.

This lets you revise the forecast before you transfer it to master schedule set 1, which is the set used by MRP, CRP, and Shop Order. You cannot copy or add a forecast if a Level 0 or Level 1 calculation is being run for one of the selected sets

Prerequisites

To perform this activity, a master schedule set must be registered in order to add, copy or reset it.

System Effects