This activity is used to change the resource capacity information automatically entered when you enter a work center, or change the load source. You can also connect additional scenarios with differentiated capacity and load sources.
This activity requires that the work center has been registered. If connecting additional scenarios the scenarios must have alredy been registered.
As a result of this activity, the system takes the specified quantity and/or efficiency into consideration when planning how much can be manufactured per day in the resource.