Net DOP Branch

Explanation

This activity is used to perform netting processes for the selected order and all its lower orders. It is also possible to perform re-netting when the quantity of the structure is changed after the release; you can also re-net after canceling netting relations.

To perform netting processes for the selected order and all its lower orders from the DOP Order page click Net, then click Branch. This can also be done from the DOP Header page after expanding the tree structure in order to display the DOP order.

Netting is performed in the following sequence:

For DOP orders where the DOP header is connected to a project, and where the Create Pegged setting is set to Pegged Orders, netting is allowed only from the project inventory. If the Create Pegged setting is set to No Pegged Orders, netting is allowed only from standard inventory. 

For project connected DOP orders, netting is performed in the following sequence:

Prerequisites

This activity requires that:

System Effects

As a result of this activity: