Perform Selective Project MRP

Explanation

This activity is used to run project material requirement planning (project MRP) for a selected set of part(s) or desired low levels. It could be within a single project or within multiple projects. The application creates project MRP planned orders and offers suggestions for planning orders for optimal manufacturing, considering material availability for the selected set of project planned parts.

The supplies and demands will be calculated by selective project MRP based on project connected demands and supplies along with non-standard planned components. Planning methods B, C, N, O, and T are excluded by selective project MRP.

Prerequisites

Selective project MRP requires the following general prerequisites:

System Effects

Status Significance
Error Some critical errors have occurred. Selective project MRP stops the process.
Warning A message posted for this process has to be reviewed by the user. This can be done by right-clicking and then clicking Show Details in the Background Jobs page, which displays the posted message in the status information table. If the user decides to continue the selective project MRP process when an error occurs, the system will post a message containing a warning.
Ready The process has been completed successfully without any errors.