Change Purchase Order Change Order Back to Planned

Explanation

When the purchase order change order has been released, it is no longer possible to register any changes to the header or lines. If you need to make any further changes to the change order you will need to demote the purchase order change order back to the Planned status. Then when the new changes are registered you can proceed in the workflow by releasing the change order once again.

Prerequisites

System Effects