Create Work Task Plan
Explanation
Use this activity to create work task plans in order to complete installation,
test and commissioning.
Prerequisites
For a work task to be created, the following should have been done:
- Project deliverable should have been defined with a project activity.
- Gross requirements should have been calculated to get the correct quantities
and dates.
The following enables work tasks to be copied from a work task template:
- A work task template must have been created in Service and Maintenance.
- A work task template connection must have been created in Project
Deliverables.
- Object property COPY_TO_MAINTANANCE must be set to
NO.
- A value for class must have been entered on project deliverable item.
System Effects
Part information on project deliverable item and where a corresponding inventory
part exist, is automatically added as material on work task plan.