Modify Requested Date

Explanation

The required date is set to the early finish date for the activity. If this date is changed, select the command Modify Requested Date to reflect the date change in its connected supply.

In Project Deliverables, the required date is set to the early finish date of the activity which has been connected to the project specific item. If this date has been changed or the project item has been connected to another activity, then a new Gross Requirements Calculation (GRC) must be run in order to reflect the new required date for the project specific item in the MPL. If a supply request has already been created for it, the Modify Requested Date command can be selected to change the required date of the existing supply. 

Prerequisites

System Effects