Modify Requested Date
Explanation
The required date is set to the early finish
date for the activity. If this date is changed, select the command Modify
Requested Date to reflect the date change in its connected supply.
In Project Deliverables, the required date is set to the early finish date
of the activity which has been connected to the project specific item. If this
date has been changed or the project item has been connected to another activity,
then a new Gross Requirements Calculation (GRC) must be run in order to reflect
the new required date for the project specific item in the MPL. If a supply
request has already been created for it, the Modify Requested Date command
can be selected to change the required date of the existing supply.
Prerequisites
- The requested date must be different from the required date.
- A DOP Header in which is either in the Created, Unreleased or Released
status must have been created for the miscellaneous part.
- A Shop Order in either the Planned, Released, Reserved or Started status
must have been created for the miscellaneous part.
- The Purchase Requisition line must be in either the Planned or Released
status. If a Purchase Order had been created from the Purchase Requisition,
the Purchase Order must be in either the Planned, Released or Confirmed
status. If execution of the change management functionality in IFS/Purchasing
require that a Purchase Order Change Order should be used to handle changes
in a Released Purchase Order, a Purchase Order Change Order must exist in
Planned status.
- Changes must have been done in the early finish date on the connected
activity, or the part has been connected to another activity.
System Effects
- The Due Date on the
DOP Header is updated according to the Required Date on the project demand
line.
- The Need Date on the Shop Order is updated according to the Required
Date on the project demand line.
- The Wanted Receipt Date on the Purchase Requisition line or the Planned
Receipt Date on the Purchase Order or the Purchase Order Change Order line
is updated according to the Required Date on the project demand line.
- The Requested Date is updated according to the Required Date on the
project demand line.