Add/ Modify Material Lines

Explanation

This activity is used to add or modify the Material lines in the Work Task Service. Modification of the material line can be done when there’s a change in the quantity of the material required, change in the required date or a change in the method of supplying the required material.

The material line can also be modified based on the location to which the material needs to be delivered. Modifying or adding a material line to enable the Direct to Service Location flow via Shipment order and Purchase Order will be as follows.

Prerequisites

System Effects

As a result of this activity,