Recalculate Post Maintenance Events

Explanation

This activity is used to recalculate the due date for post maintenance check events.

If a post maintenance check event has been completed earlier than the calculated due value or due date, the calculation of the next due value or date will be adjusted accordingly. Note that no adjustment will be done if a post maintenance check event is performed too late.

To perform this activity, search for the serial for which you want to recalculate post maintenance events from the Serial Maintenance page.

Prerequisites

System Effects