Maintenance resources are resources which have been defined in IFS/Enterprise/Resource/Resource Details to be used in Service and Maintenance (including Forward/Line Maintenance). The resource types include persons, person groups, tool/equipment and tool/equipment groups. When specific criteria are met the resources can be entered on a resource demand line and be assigned to work assignments on a work task.
Person and Tool/Equipment:
To use a resource in a work task resource demand or work assignment the following is required in Resource Details:
Note: In addition to above:
Resources of type Tool/Equipment's can also be used in Forward/Line Maintenance. The same prerequisites as above is valid, with the difference that you can enter the resource demand without any consideration to sites. To be able to allocate a tool/equipment to a FLM work task, the site connection is needed.
To use a resource in a work task resource demand, the following is required in Resource Details:
In general, resource groups cannot be allocated to work assignments. However, if IFS/Maintenance Planning Board is used, resource groups are possible to allocate.
To allocate a resource group in a specific site in MPB, in addition to the prerequisites for persons group and tools/equipment group which are mentioned above, the following is needed in the Connections page in Resource Detail page for the Specific site connection:
Resource groups of type Tool/Equipment's can also be used in Forward/Line Maintenance. The same prerequisites as above is valid, with the difference that you can enter the resource demand without any consideration to sites.
If tool tracking is used in tool/equipment groups, Tool Tracking needs to be set as Track Check Out/In in the Resource Details/Maintenance page for the resource groups of type Tool/Equipment.
In general, resource availability is taken from resource Calendar. There are general flows of fetching calendar as below.
Availability of Person
Availability of Tool/Equipment
Availability of Person/Tool Group
To be able to achieve correct results in resource allocation there is a pre-requisite to have the capacity calculated for the resources. Generated capacity calculated for a resource is a pre-requisite for the following allocation functionalities:
The resource capacity is calculated based on the resource schedule. If the Use HR Schedule option is enabled on resource and employee is connected to the resource has an HR Schedule defined in the Employee File this Schedule is used as the base for the capacity. If the Use HR Schedule option is disabled then the Work Time Calendar defined for the resource is the base for the calculated capacity. The resource capacity is used in the allocation process in Service and Maintenance to define the working and non-working time for the resources.
To calculate the resource capacity for the resources it is needed to run the Calculate Resource Capacity for the resource structure where the resources is connected to. In Application Base Setup/Enterprise/Resource/Resource Details the option is there as a command button option to Calculate Resource Capacity this calculation can be done for a specific resource or for the full resource structure. In the dialog opened from this option there is also an option to setup a background job to continuously calculate the capacity for a certain structure.