Decommission Compatible Unit Revision
Explanation
This activity is used to decommission a compatible unit revision thereby
scrap the connected asset. Perform the activity by selecting the Compatible
Unit from the Compatible Unit Navigator and changing
its Status to Decomissioned.
Prerequisites
- A compatible unit revision must exist, which is created for the purpose
of decommissioning. i.e. This compatible unit revision must have
another revision of it which is in status Active.
- Work orders connected to the execution items, which were used to decommission
the compatible unit must be completed.
- The connected design object and equipment object should have the design
status and operational status, PlannedForScrap and Out of Operation
respectively.
System Effects
- The status of the compatible unit will be set to status Decommissioned.
- Sub Units connected to the decommissioned compatible unit will also
be decommissioned if they satisfy the above prerequisites.