This activity is used to add new contract items in order to
plan and estimate the change. It is possible to add new items to an existing
contract line of the contract revision. It is also possible to create new lines
and then add new items connected to that.
New items are added with Expected values during the initial
statuses (ie. Preliminary or Analysis in Progress
status) of the Contract Change Order. Requested
values could also be added during the same statuses but that is optional.
Expected values are considered to calculate the Net
Change in
Preliminary or Analysis in Progress status
of the CCO.
Once the CCO becomes Analyzed status,
Agreed values can be added and from that point onwards the
Net Change is calculated using the Agreed
values.
Note:
Currently it is possible to plan and estimate a contract
change using new contract items only. It is not possible to modify or delete
existing contract items through a CCO.