Enter Material Requisition Line

Explanation

The material requisition is built in two levels, consisting of a requisition header and one or more requisition lines. The second step in a new entry is to enter material requisition lines.

For condition code enabled parts, you can specify a condition code in the Condition Code field. The supply code of the inventory part is entered in the Default Material Requisition Supply field on the Inventory Part/Supply and Demand Control section. You can alter between inventory order and purchase order. The supply code indicates whether the part will be issued from inventory or a requisition should be created to purchase the part. However, you can make a single occurrence change on the order line by using the Supply Code list.

If you intend to connect the material requisition line to a project activity, first set the supply code to Inventory Order, and then connect the line to a project activity. Upon connecting, the supply code will be changed to Project Inventory; if required, you can change it back to Inventory Order
If you have connected the line to a project activity and set the supply code to Project Inventory, parts can be issued only from the project inventory of the connected project. If you set the supply code to Inventory Order, parts can be issued from standard inventory on behalf of the connected project activity.

Prerequisites

  • Purchase Part - The planned part is purchased. 
  • Manufacturing Structures - The planned part is manufactured.
  • Supplier Parts - The planned part is sourced from a supplier split.
  • Make/Buy Splits - The planned part is both purchased and manufactured.

System Effects