Activity Enable MSO Dataset
Explanation
Use this activity to connect a site to IFS PSO ( Planning Scheduling and
Optiomization) engine.
MSO uses PSO as its scheduling server.
Prerequisites
- MSO solution uses IFS Planning Scheduling and Optimizaiton ( PSO) solution
as its scheduling engine. Therefore it is mandatory to have a online PSO
scheduling server running to execute this activity.
- Finite Scheduling Basic Data must be defined for the site
System Effects
For Automatic MSO Mode
- The dataset which is created for the MSO site will be enabled
- Background jobs will be created. It is required to make sure that these
bacground jobs are properly executed.
- Application messages are created. It is requred to make sure that these
application messages are properly processed.
- Scheduling requrest to create a fininte schedule for the site will be
sent automatically. It is required to make sure that all the bacground jobs
and application messages are executed sucessully