Close Activity

Explanation

Perform this activity to set the selected project activity to the Closed status. Once an activity is in Closed status, it can only be demoted to the Completed status.

The Actual Finish date is set to the Early Finish date if Actual Finish has not been set manually.

Note: You are able to to check for any incomplete work on the activity before closing the activity. This can be done in the Unfinished Activity Work page.

To close an activity, select the activity to be closed and select Close from the Status command button.

Prerequisites

System Effects