Copy From Project Forecast

Explanation

This activity is used to copy forecast lines from a project budget/forecast version into a new project cash forecast.

The New Project Cash Forecast assistant is used to create a new cash forecast, and there is an option to copy from an existing project forecast version.

The forecast lines with details (sub project, activity, cost/revenue element and dates) will be copied over to the new cash forecast. The EAC value from the project forecast lines will be copied to the Total Amount column on the new cash forecast lines. The period spread values will not be copied.

 Project forecast lines with a CBS node instead of a cost/revenue element will not be copied.

Prerequisites

System Effects

 Forecast lines from the selected budget/forecast to copy from are inserted into the destination cash forecast.