Execute Update Project Forecast at Work Recording Summary

Explanation

This activity is used to update the calculated periodic progress values to selected Project Forecast. This can be achieved by performing Update Project Forecast command in Work Recording Summary page.

When the selected Project Forecast is created using copied with details option then the selection of Cost or Revenue option and the levels will not be allowed to change.

Calculated Date of the Schedule of Work Production should be within the range of the Cut Off Date of your selected Project Forecast.

Prerequisites

Execute Calculate Value should be performed.

Periodic review Project Forecast should be ready.

System Effects

Progress % of the selected Project Forecast Item lines will be updated based on the Work Record progress.