Perform this activity to report progress for a resource assignment on an activity. There are two ways of obtaining progress for a resource: manually; or through project reporting, i.e., when the employee connected to the resource group reports his or her time on the activity.
To report progress manually, go to the Planning tab in the Project Resource Planning page. Select the relevant record and enter the progress value in percentage.
To obtain progress through project reporting, follow the steps described in activity Register Project Time, then follow up the progress calculated for the selected activity.