Use this activity to report a document package's progress.
The document package feature allows you to monitor the weighted average progress of a document package. To indicate the progress, the package feature uses a set of common milestones, where each milestone has an associated progression. Typical milestones and their associated progressions are:
You can enter planned cost and hours for each of the documents in a document package. If you want to connect this document package to a project activity, you will have to define a project cost element for the cost and hours.
Activity can be carried out by selecting the document records and edit the Milestone Number field to reflect the progress