Evaluate and Add Modification Events to the Work Scope

Explanation

This activity is used to add one or more modifications to a work scope. Usually the mandatory modifications, due modifications, and modifications included in the customer baseline (i.e., those which have not been complied with as yet) are transferred to the work scope. Apart from the mandatory modifications and due modifications, you can choose the modifications you want added to the work scope. For instance, if a modification which is not due nor assigned to a serial exists, and this modification is applicable for a particular serial, you can choose to add the modification to the work scope, as per your requirements.

To add modifications to a work scope, click Assign Events to Work Scope in the Manage Work Scope Events page. In the Modifications step of the assistant, select a suitable filter to populate modifications in the list. You can view modifications assigned to the overhaul object and its structure and modifications included in the baseline. The list will also include modification not yet due (where pending maintenance events are not yet generated for the modifications). Following options can be used to include modifications to the work scope:

To view modifications that have been previously complied with for the overhaul object and its structure, click the Manage Work Scope Events/PCW Modifications tab. If you want to create a decomply event, select the relevant modification in this tab and click New Event for Decompliance.

To remove a modification from the work scope, select the relevant modification in the Included Mx Events tab and click Remove Events from Work Scope.

Note: Only one revision of the modification can be included in the current or any other ongoing work scope for the overhaul object and its structure. To include a new revision of the modification, the previous revision must either be removed or canceled from the relevant work scope.

Prerequisites

System Effects