Update Resource Capacity
Explanation
This activity is used to update the Resource Capacity if some Work
Tasks are left unplanned and the reason appears to be limitation in
available Resource capacity.
It is important to review following, if resources capacity appear inadequate:
- Used in Maintenance must be Yes for
all the resource groups from which resources are used.
- Individually planned person resources must be connected to the relevant
Maintenance Organization(s)
- Make sure all individually planned resources have the resource schedule
generated. This can be viewed in the Resource Availability
page. If the schedule not available, generate the schedule.
- Make sure all resource groups planned on group level
(capacity calculation base = Group ) have the planned site(s)
connected and also have a generated calendar connected.
Prerequisites
- Work Planning and Scheduling Dataset has been enabled and
sent to IFS Planning & Scheduling Optimization (PSO) engine and schedule returned by PSO has been saved in the IFS
business system. Analyzing the plan result found some discrepancies.
System Effects