Update Task Value Configuration

Explanation

This activity is used to assign the scheduling priority of Work Tasks. It is achieved by adjusting the Per Hour Base Value defined on the Work Planning and Scheduling Dataset. The default base value defined on the Dataset is assigned to all the Work Tasks planned using the Work Planning and Scheduling Dataset. That value can be overridden by defining hourly base value on Work Type/ Priority/ Object Criticality/ Event after enabling those tabs in the Work Planning and Scheduling Dataset page.

Prerequisites

System Effects

Work tasks with higher calculated base value (Per Hour Base Value * Duration) has a higher probability of getting scheduled, over the Work Tasks that have a lower value.

ex:

Work Planning and Scheduling Dataset configuration:

  per hour Base Value
Default 20000
Work Type = 80 30000
Priority      = 1 50000

Work Task configuration:

Work Task No.  Duration Work Type Priority Configured Task Value Result
1100 1     20000
1200 1 80   30000
1300 1 80 1 30000 + 50000 = 80000

For above example data, Task No 1300 has the highest probability of getting scheduled and Task No 1100 has the lowest probability.