Activate Item

Explanation

You can incorporate items in the work scope again, when the work with the item has been resumed. All items by default are created as Active and incorporated in the cost calculation. It is possible to set an inactivated item back to active as long as its top item isn’t Confirmed for any version. On a top item, click Item Status, then Activate. On an item in the tree structure, click Item, then Activate.

Prerequisites

This activity requires that an estimate header that does not exist in status Confirmed, Completed, Closed or Cancelled. At least one item must exist as Inactive and it must be in status InProgress or Calculated.

System Effects

As a result of this activity, an item record is again incorporated in the work scope and considered when performing a calculation. All items in the branch are set to Active.