Connect Work Task Templates
Explanation
Use this activity to connect work task templates to a PM program.
You can connect work task templates
to a PM program. A single work task template can be connected to many PM programs.
Prerequisites
- Work Task templates must have been defined
in IFS/Preventive Maintenance.
- The work task templates defined should be active and
valid.
- Sites need to be specified in Valid For Sites tab on the PM
Program.
- Item Classes need to be specified in Applicable Objects
tab on the PM Program.
- The PM program should be in the Preliminary status.
System Effects
Work Task templates will be connected to the PM program.
Procedure
Connecting one work task template at a time:
- Open the
PM Program page, and
create a new PM program or query for an existing one.
- Click Valid For Sites and create a new record if
there are any more sites for which the PM program will be valid.
- Click Applicable Objects and create
a new record if there are any more process classes and item classes for
which the PM program will be valid.
- Go to Work Task Templates tab and create a new record.
- Enter the task template ID and revision in the
relevant fields. Use the List of Values. Repeat steps 4 and 5 as often as required.
- Save the information.