Approve Resource Breaks

Explanation

This activity is used to approve a resource break which is in Proposed state. The status of the break converts to Unscheduled.. In the case of Advanced Planning Board (APB) sites, only a state change occurs and these Unscheduled resource breaks will be loaded to the APB thereafter. Resource breaks are taken into account only when orders are scheduled using Constraint Based Scheduling (CBS), not when using the Shop Order Infinite Scheduler.

Prerequisites

The activity requires the existence of a resource break in Proposed state.

System Effects

As a result of this activity: