Create APB Site

Explanation

Use this activity to create a site that can be used by IFS Constraint Based Scheduling (CBS). This activity must be performed in order to set up a site to use Constraint Based Scheduling via Advanced Planning Board. This task is to be performed by a system administrator or equivalent person.

Prerequisites

This activity requires that a site must have been created in the Site page.

System Effects

As a result of this activity the system creates a site that can be used with the Advanced Planning Board.