Save Schedule Result to Database
Explanation
This activity is used to save your schedule changes to the database.
Prerequisites
This activity requires:
- A shop order schedule has to be created, when working with the Advanced Planning Board.
- At least one unsaved change to the schedule.
- When working with the APB, that no changes be made outside the APB to
the items that you are trying to save. If there is a change in one or more
of the items, you will be notified of the modifications and will not be
allowed to save them via the APB. The items which do not have modifications
can be saved.
System Effects
As a result of this activity:
- The schedule is saved to the database. The start and end times of shop
orders or operations will be updated if they have been modified.
- You will be notified if any of the changes cannot be saved successfully.
If you are using the APB, any errors will be displayed in the
Error Message page.
- The value in the CBS Scheduled field in the Shop
Order/Operations tab will be set to Scheduled.