Change Shop Order Scheduling Direction
Explanation
Use this activity to change the scheduling direction of a shop order. You
can select one of below values in the Scheduling Direction field:
- Forward Scheduling - The shop order is scheduled to start on
its Earliest Start Date.
- Backwards Scheduling - The shop order is scheduled to finish
before its Need Date
- Manual Scheduling - The shop order is scheduled based on
manually defined start/finish dates on its operations.
To change the scheduling direction from the Shop Order,
Shop Orders or Production Line Management/Shop Orders
pages, select a new value in the Scheduling Direction field.
To change the scheduling direction from the Inventory Parts
Intraday Availability page, expand the line for the relevant part
and select the supply line from the shop order you want to update. Click
Edit Shop Order and select a new value in the Scheduling Direction field.
Prerequisites
The shop order must have been created.
System Effects
- The Scheduling Direction field is updated and the operations
for the selected shop order are rescheduled.
- If the shop order pegged to a DOP order and the site is set to replicate changes,
Start Date and Due Date fields of the DOP order are updated
accordingly.
- A message asking you to review the peggings will be displayed if the shop
order is pegged.