Check APB Assigned Resources per Operation

Explanation

Use this activity to study the resources assigned to each operation by Advance Planning Board (APB), as a result of constraint-based scheduling.

Shop order infinite scheduler assign a resource, but it will not consider the finite/infinite resources when scheduling. APB will book finite resources without overloading them and thereby creating a finite schedule for operations. These resource assignments can be investigated using this page.

Prerequisites

Operations should have been scheduled by IFS Constraint based scheduling tool, Advance Planning Board (APB) and saved back to the database.