Create Shop Order Requisition Manually

Explanation

Use this activity to manually enter a shop order requisition. You can also generate a shop order requisition from MRP, Project MRP(PMRP), Master Scheduling, Order Proposals, Next-Level and similar planning engines.

To create a requisition manually, create a new record and enter the required part, quantity and due date.

Prerequisites

The part being requisitioned must have a valid part revision on the start date.

To create a requisition manually from the Production Line Management page, a routing revision/alternate valid for the production line must have been selected using the Routing Operation Parameters dialog.

If the part is serial tracked and has either Structure Effectivity or Routing Effectivity set to Serial, you must reserve serial numbers for the entire lot size on the shop order requisition before you can either create a shop order or merge into a shop order. The serials assigned to the shop order requisition must be for a single structure or routing alternative.

System Effects