Activity Finite Schedule Shop Orders
Explanation
Use this activity to schedule shop orders in MSO static scheduling mode
This activity is not applicable for MSO automatic scheduling mode as MSO
create finite schedule for shop orders as an when they are created or modified
The schedule is created and optimized baed on:
- Shop order scheduling data such as, Need date, Earlist start date, Loti
size, scheduling direction and constraints defined in routing.
- Site scheduling data settings such as Scheduling quality and maximum
processing time.
- The Site scheduling optimizaiton parameters like, set up matirx, project
activity dates, and including relased orders or not.
Prerequisites
- Finite schduling basic data should be created for the site
- The site should be set to use MSO static scheduling mode
- The site should be connected and and the PSO server connected to the
site should be running ( Check server availability)
System Effects
As a result of this activity a finite schedule is created and saved back
to he database. The the order of execution ( schedule sart and fininish times)
will be set. Upon loading to shop floor work bench , these operations will be
visible for shop floor workers in the order that they are scheuled for them
to execute.