Report Machine Time

Explanation

Use this activity to report machine time for a shop order operation. It can be the time needed to set up an operation before manufacturing begins (setup time) or the time of the actual manufacturing (runtime). Machine time is booked on a work center resource which does not have to be a machine, but may also represent the physical location where the operation is performed. Resource share indicates how much the work center resource was utilized during its duration.

To report machine time for a shop order operation from:

Prerequisites

System Effects