Report Disposition Complete
Explanation
This activity is used to report the disposition of the
material review board (MRB) parts as completed. Click Complete
on the Disposition tab to complete the disposition
item when the disposition activity has been performed in the related
object.
This activity contains a Security Checkpoint which can be activated by an
administrator. With an activated security checkpoint on a function you will have
to authenticate yourself again in order to fulfill the function. Additionally,
whenever a security checkpoint is successfully passed a security checkpoint log
is written, creating an audit trail of what is done.
Prerequisites
- At least one disposition item with identified disposition part(s)
exists for the MRB case.
- If the disposition code requires scrapping verification, the
quantity dispositioned with this code must have been scrapped if the MRB
case is created against a shop order.
System Effects
- Disposition completed will be set for a disposition item.
- The values for the Completion Date and Action Completed By
fields will be automatically generated by the system.
- The disposition information can not be updated after the disposition
item is completed.
- The parts that have been registered as dispostioned will no longer be
controlled by the MRB. These parts can be further processed from their
source (inventory part in stock, purchase order receipt, or shop order).