This activity is used to reserve material automatically for one or more selected material lines. All material for the lines that have not been reserved yet will be reserved.
The supply code of the selected material lines is considered when reserving material.
The value in the Reserve/Issue Method field of the shop order material line is considered when automatically reserving/issuing material. This value determines how to reserve/issue material to the shop order.
For operation connected material, the option selected in the Outside Reserve/Backflush drop-down on the Work Center page is considered when automatically reserving material. This value determines how the reserve/backflush of material is allowed from locations other than work center inbound locations.
If the Shared Location option is enabled on the Locations tab on the Work Center page, material can be reserved/issued to any demand. If not selected, only the material demands from operations that are connected to the work center will be allowed to reserve/issue material from this location.
If the shop order is connected to a batch balance ID and the Allow reserve and issue from lot/batches outside the batch balance option is enabled on the Site/Manufacturing page, reservation of the component which the preceding balanced shop order is supplying is limited to the lot/batch numbers received from this shop order. Note: The shop order is limited to reserve supply received from the preceding shop order, however any other shop order without a connection to a balance ID is allowed to reserve the same material.
To reserve shop order component(s) from:
A. Project inventory connected to the same activity.
- Issue from location identified for the shop order component.
- Inbound locations for the identified work center location for the operation associated with the component, if any.
- From the Floor Stock location type.
- From the Picking location type.
B. If A was not fulfilled and the supply code is Project Delivery
- Try to reserve components from the demand activity sequence using the project delivery structure.
C. If A or B was not fulfilled, look for the project inventory connected to a different activity, but belonging to the same project
- Issue from location identified for the shop order component.
- Inbound locations for the identified work center location for the operation associated with the component, if any.
- From the Floor Stock location type.
- From the Picking location type.