Reschedule All Past Due Shop Orders

Explanation

Use this activity to reschedule all past due shop orders for a site. If a shop order has a Finish Date earlier than today, that shop order will be considered as a past due order and all such orders for the selected site will be rescheduled with scheduling direction Forward and the Earliest Start Date with today's date. Start and finish date of the order(s) will be calculated based on the infinite scheduling or the CBS server logic if enabled for the site. Depending on the settings in Site/Extended Site Info/Shop Order Replication the new shop order dates may be replicated to pegged customer order lines and DOP orders.

It is also possible to schedule new reschedule all past due shop orders for a site using this assistant.

Prerequisites

A shop order with a finish date earlier that current date must exist.

System Effects

As a result of this activity: