Reschedule Shop Order Operation

Explanation

This activity is used to reschedule a shop order operation to a new date/time. The activity can be performed either using the Reschedule command in the Machine Load and Labor Load charts, or using drag-and-drop in the Machine Operations Scheduling and Labor Operations Scheduling charts.

From the Machine Operations Scheduling and Labor Operations Scheduling charts it is also possible to schedule the operation to a new resource on the same, or a different work center.

Note: New start and finish date will be based on the infinite scheduling logic and may differ from the value seen in the dialog. For instance, if the provided new start date is on a non working date, the operation will receive a new start date corresponding to the first available work date/time from the date provided.

Prerequisites

System Effects

If Forward Scheduling is selected:

If Backward Scheduling is selected: