Schedule Shop Order(s)
Explanation
This activity is used to calculate the start and finish date of the
operations and the shop order, according to the schedule direction.
Efficiency, utilization, maximum hours of operations as well as queue time,
transport time and so on have been taken into account when scheduling the
shop order.
To schedule shop order(s) from:
- Shop Order and Disposition Shop Order
pages, click Schedule.
- Shop Orders and Production Line Management/Shop
Orders pages, select the relevant shop order(s) and click
Schedule.
- Select Schedule Using Existing Shop Order Settings if you want
to base the scheduling on the existing Schedule Direction, Earliest
Start Date and Need Date of the shop order(s).
- Select Forward Schedule From Earliest Start Date and specify
an earliest start date if you want to change Schedule Direction to
Forward Scheduling and schedule the shop order(s) from this date.
- Machine Availability Summary, Machine Load, Labor
Load, Machine Operations Scheduling and Labor Operations
Scheduling charts. Select the segments representing the relevant
shop orders and click Schedule Shop Order.
- Select Schedule Using Existing Shop Order Settings if you
want to base the scheduling on the existing Schedule Direction,
Earliest Start Date and Need Date of the shop
order(s).
- Select Forward Schedule From Earliest Start Date and
specify an earliest start date if you want to change Schedule
Direction to Forward Scheduling and schedule the shop
order(s) from this date.
Prerequisites
An open shop order must exist.
System Effects
- The shop order(s) will be (re)scheduled with the new start and finish
dates based on the infinite scheduling logic.
- If Schedule
Direction is set to Forward Scheduling the order will be scheduled
from its Earliest Start Date and forward.
- If Schedule Direction
is set to Backwards Scheduling the order will be scheduled backwards
from its Need Date.
- Manual scheduling changes done to the operations of the order will be
overwritten.
- Operation scheduling done by IFS/Advanced Planning Board
will be overwritten.