Transfer Demand to Purchase Requisition

Explanation

This activity is used to transfer an existing demand from a shop order requisition to a purchase requisition. This may occur when the parts to be manufactured before, are now to be purchased instead.

To transfer a quantity from a shop order requisition to a purchase requisition from the :

In the dialog, enter the quantity you wish to transfer in the Qty to Transfer field. The quantity cannot exceed the current quantity on the shop order requisition. If required, change the requisitioner in the Requisitioner ID field. This may be required, for example, to prevent automatic removal of the created purchase requisition when the next MRP is being run.

Note: The shop order requisition load will not be updated until the Capacity Requirements Planning (CRP) calculation has been executed.

Prerequisites

System Effects